Bridge parapet works on the westbound carriageway of the A14 near junction 18 (Spaldwick) are due to commence on 14th October 2013 and are expected to take approximately five nights to complete. The works will involve pre-replacement testing of the parapets. The works will be undertaken overnight and the working hours will be: 10pm to 5am Monday to Friday nights. During the works, there will be lane closures in place where the current narrow lanes are situated and the 50mph speed restriction will remain in place.
The parapet replacement works will commence on 24th October until 11th December. These works will be undertaken during the day with the existing narrow lanes. These works will invariably generate some noise and disruption for those living in the adjacent areas.
If you have any queries concerning this scheme, please contact CarillionWSP on 01767 684633 during the hours of 9am and 5pm or the Customer Care department at customercare@carillionwsp.com, or alternatively the Highways Agency Information Line on 0300 123 5000.